Judgment delivered by the Supreme Court of India Dyna Technologies Pvt. Ltd vs. Crompton Greaves Ltd.

[Civil Appeal No. 2153 of 2010; 2019 SCC OnLine SC 1656]


In this matter, the principal contract was entered into between DCM Shriram Aqua Foods Limited and M/s. Crompton Greaves Limited (Respondent) for an aquaculture unit to be set up by DCM Shriram Aqua. Dyna Technologies Pvt (Appellant) was successful in getting work order from the Respondent for construction of ponds, drains, channels and associated works.
 
The work order awarded by the Respondent to the Appellant contained a clause providing for termination of the contract by the Respondent without any liability for compensation for premature termination. The said clause was exercised by the Respondent, and the contract with the Appellant was terminated.
 
The Appellant raised several claims on account of losses suffered due to idle charges, due to unproductivity of men and machinery which could not work due to hindrances, loss of profit due to dissolution of contract, and costs and interest on the above claims.
 
The claim relating to ‘unproductivity of men and machinery’ came to be allowed by the Arbitral Tribunal, and subsequently affirmed in the petition under Section 34 preferred by the Respondent. [The decision of the Tribunal on the rest of the claims were not subject matter of dispute, either on account of having been settled between the parties or having been accepted by the parties.]
 
The Division Bench of the High Court partially allowed the appeal preferred by the Respondent under Section 37, and set aside the award of compensation on the aforesaid claim, having concluded that the award did not disclose sufficient reasons for the decision.
 
The argument of the Appellant that in the aforesaid view of the matter, the Court was empowered to exercise Section 34(4) was also rejected by the High Court. It was of the view that Section 34(4) of the Act was not necessary as the compensation could not have been claimed on account of the specific prohibition on claim of compensation in the work order.
 
The following principles of law were laid down by the Supreme Court, on a detailed examination of the subject:
 
I.              The Supreme Court examined the judicial and legislative history of Section 31(3) of the Act, which called upon the arbitrator to provide reasons for the award. The Court concluded that the mandate under section 31(3) of the Act is to have reasoning which is intelligible and adequate and which can, in appropriate cases, be implied by the Courts from a fair reading of the award and documents referred. The Court set out three characteristics of a reasoned award, viz., that a reasoned award ought to be: proper, intelligible and adequate:
(i)                 If the reasoning in the order is improper, it reveals a flaw in the decision-making process. If the challenge to an award is based on impropriety or perversity in the reasoning, then it can be challenged strictly on the grounds provided under section 34 of the Act;
(ii)               If the challenge to an award is based on the ground that the same is unintelligible, the same would be equivalent of providing no reasons at all;
(iii)             Whereas concerning the challenge on adequacy of reasons, the Court while exercising jurisdiction under section 34 of the Act, has to adjudicate the validity of such an award based on the degree of particularity of reasoning required having regard to the nature of issues falling for consideration. The degree of particularity may not be capable of definition, and thus in a case where there were gaps in the reasoning in an award, the documents relied upon could be looked at so as not to result in setting aside of the award in a casual manner
 
II.           On Section 34(4) of the Act, the Court opined that the provision could be resorted to in the event of gaps in reasoning in the award. The Court noted that the legislative intent underlying the provision was to make the award enforceable. In the facts of the present case, the Court opined that in view of the finding that there were gaps in the reasoning, the High Court ought to have considered exercise of the power under Section 34(4).
 
The Supreme Court, in the facts of the case, concluded that the award was unintelligible and confusing as the award was muddled with facts, contentions and reasoning without appropriately considering the complexity of issue involved. The award was accordingly set aside.
 
The exercise of power under Section 34(4) was not deemed appropriate given the fact that the litigation had been pending for 25 years. In the facts, it was considered appropriate by the Apex Court to direct the Respondents to pay a sum of Rs.30 Lakhs to the Appellant in full and final settlement.
 



Judgment delivered by the Delhi High Court Power Mech Projects Ltd. vs. SEPCO Electric Power Construction Corporation

[O.M.P. (I) (COMM.) 523/2017, I.As. 11128/2018, 4259, 5185 and 7203/2019; MANU/DE/0553/2020]



This case arose out of an arbitral award dated 17.10.2017 for a sum of Rs. 142,41,14,499/- in favour of the Petitioner (hereinafter, “PowerMech”) and against the Respondent (hereinafter, “SEPCO”). SEPCO had challenged the award by way of an application under Section 34. During the pendency of the same, PowerMech filed a petition under Section 9(ii)(b) praying for certain interim directions for securing the awarded amount. It is a matter of record, and of relevance that no proceedings under Section 36 for enforcement were initiated by PoweMech. Several orders did come to be passed on the Section 9 application, whereby a variety of directions were issued to SEPCO to secure the awarded amount. Notwithstanding the compliances by SEPCO with the aforesaid directions by deposit of monies and/or execution of bank guarantees from time to time, the entire awarded amount was not secured by SEPCO.
 
The limited issue decided vide this order was as to whether the challenge by SEPCO to the award could be heard on merits without it first securing the amount awarded in favour of PowerMech, in entirety.
 
The submission of SEPCO, broadly, was that Section 34 did not contain a provision in the nature of pre-deposit of the awarded amount for hearing of the challenge. This not having been intended, the discretion was left to the Court to determine measures necessary for determining the conditions for staying operation of the award. PowerMech sought to establish from the facts of the case, the necessity to secure the awarded amount in entirety. The applicability of Section 9 being filed post-award, was also emphasized, on behalf of PowerMech, to contend that the objective of the provision was to ensure that the successful party was able to realise the fruits of the arbitration proceedings, viz., a step in aid for enforcement of the award.
 
It was held by the Court:
(i)                 that the requirement for securing the awarded amount to the extent of 100% could not be said to be mandatory in law and the amount of deposit required to be made was to be considered in the facts and circumstances of the case and was upto the discretion of the Court.
 
(ii)               that in the facts of the case at hand, the chronology of facts of the case revealed that SEPCO [a Chinese company] did not have any immovable assets in India. Though it had filed an affidavit to the effect that it had ongoing projects in India, in the opinion of the Court the ongoing projects could not be accepted as security to ensure that the Award would be enforceable. The existence of movable assets was also held to be insufficient security for the purpose of securing the awarded amount;
 
(iii)             Furthermore, the attention of the Court was drawn to the recent orders of Hon’ble Supreme Court in SREI Infrastructure Finance Limited vs. Candor Gurgaon Two Developers and Projects Pvt. Ltd. being SLP(C) No(s). 20895-20897/2018 where in an appeal, the Supreme Court had directed 100% deposit of the award amount. Similarly, in case of Manish vs. Godawari Marathawada Irrigation Development Corporation, being SPL(C) Nos. 11760-11761/2018, the Bombay High Court had ordered 60% deposit but the Supreme Court held that there should be a 100% deposit being a money decree.
 
In view of the above, the Court directed SEPCO to deposit the entirety of the awarded amount, within four weeks, after adjustment of the amounts deposited.


 

Judgment delivered by the Bombay High Court (Nagpur Bench) Omprakash and Ors. vs. Vijay Dwarkada Varma

[Writ Petition No. 4248 of 2019; MANU/MH/0543/2020]
 

In this case, the question that arose was the appropriate place for initiation of proceedings under Section 34 of the Act, where the ‘seat’ of arbitration was not expressly set out.
 
It was undisputed that the entire arbitration proceedings took place at Nagpur and that award was pronounced and signed by the arbitrator at Nagpur, albeit without specifically stating the place of signing of the award as required under Section 31(4). Aggrieved by the said award, the Petitioners filed an application under Section 34 of the Act before the Court at Malkapur. The Respondent raised an objection of jurisdiction, praying for rejection of the aforesaid application, as being untenable before the Court at Malkapur and alternatively requested that the Petitioners may be relegated to the proper Court. The Court below allowed the application and found that the Court at Malkapur did not have jurisdiction to entertain the application under section 34 of the Act, because the place/seat of arbitration was at Nagpur and the award was pronounced and signed by the arbitrator at Nagpur. Consequently, the application under section 34 of the said Act was dismissed for want of jurisdiction. Aggrieved by the same, the Petitioners filed the writ petition before the High Court.
 
The Court by following the law laid down in the Bharat Aluminum Co. v. Kaiser Aluminium Technical Services Inc., (2012) 9 SCC 552 held that it was a facet of public policy that only one Court should have jurisdiction to set aside an arbitral award.
 
The Petitioner’s case was premised on the following grounds:
(i)                 In the facts, the seat of arbitration not having been specified by the parties, or by the Court while appointing an arbitrator under Section 11, the arbitrator was expected to determine the place of arbitration while relying on Section 20(2). This was also not done. Such being the case, by application of the definition of ‘Court’ under Section 2(e) to the facts of the case, the appropriate Court was Malkapur, and therefore the application ought to have been entertained by the said Court;
(ii)               Reliance was placed on the decision of the Supreme Court in Videocon Industries Ltd. v. Union of India [2011(6)SCC 161] to contend that mere holding of the proceedings at Nagpur could not amount to designation of Nagpur as the ‘seat’ of arbitration.
(iii)             Reliance was placed on the Supreme Court Constitution Bench decision in Bharat Aluminium Company Ltd. v. Kaiser Aluminium Technical Services Inc. [2012(9)SCC 522] for the proposition that in such facts, the Court at Nagpur as well as the Court at Malkapur would have jurisdiction to entertain the application under Section 34. The decision in Union of India v. Hardy Exploration & Production India Inc. [2019(13)SCC 472] was also relied upon for the said proposition.
 
Per Contra, the Respondent relied on the Supreme Court decision in BGS SGS SOMA JV v. NHPC Ltd. [MANU/SC175/2019] to argue that the Court at Nagpur alone had jurisdiction to entertain the application, Nagpur undeniably being the seat and the place of the arbitration.
 
BGS SGS SOMA (supra) was sought to be distinguished by the Petitioner on the facts of the case (in that, in that case the parties had mentioned two places as the places of arbitration, and in the present case there was no mention whatsoever) and also by stating that in the absence of a determination by the arbitrator under Section 20(2) in this case, it could not be said that Nagpur was the place of arbitration merely because the award was signed there.
 
After a detailed examination of the applicable provisions of the Act and the aforementioned decisions of the Supreme Court, it was held that:
 
(i)                 The fact that the parties had not specified Nagpur to be the place of arbitration could not lead to the conclusion that it was not the place of arbitration, if it could be so ascertained to be the place from the conduct of the parties, as in the present case. The issue of ‘determination’ of the place of arbitration by the arbitrator would arise only in a case where there existed a dispute as such, which was not the case here;
(ii)               Since the entirety of the arbitration proceedings took place at Nagpur without any objection as to the place of arbitration by either side, it could be said that Nagpur was chosen as the place of arbitration in terms of Section 20(1);
(iii)             The decision in BALCO, explained further in BGS SGS clearly applied to the facts of the case, and jurisdiction exclusively vested in the Courts in Nagpur to test the award under Section 34, in view of the fact that the place of arbitration was Nagpur;
(iv)             The decision of the Malkapur Court having been affirmed, the High Court held that the appropriate course open to it was to return the application for presentation to the proper Court (viz., Nagpur), instead of dismissal of the application, as was done.


 

Judgment delivered by the Calcutta High Court Sirpur Paper Mills Ltd. vs. I.K. Merchants Pvt. Ltd.

[A.P. No. 550 of 2008; MANU/WB/0040/2020]
 

An issue arising out of the interplay of the Insolvency & Bankruptcy Code, 2016 (“IBC”) and the Act arose for consideration of the Court in the following facts:
 
An arbitration was between the petitioner and respondent culminated in an award in 2008 in favour of the respondent. The application for setting aside the award was filed in 2008 itself by the petitioner. Some operational creditors of the petitioner initiated proceedings under Section 9 of the IBC against the petitioner in 2017, resulting in a moratorium which remained operative till 19.7.2018 (on which the resolution plan for the petitioner seems to have been approved). When on 11.12.2019 the application under Section 34 was taken up for hearing, the petitioner contended that the application could not be proceeded with since the petitioner had undergone CIRP and since the respondent had not filed a claim in the said CIRP in terms of the award in its favour. The respondent on the other hand relied on the Supreme Court decisions in K.Kishan vs. Vijay Nirman Company Private Limited (2018) 17 SCC 622 and Mobilox Innovations Pvt. Ltd. Vs. Kirusa Software Put. Ltd.(2018) 1 SCC 353 to claim that in view of these decisions, the respondent could not have filed a claim in the CIRP on the basis of the award.
 
The question which arose was whether the present application under Section 34 of the Act should be kept in abeyance by reason of the provision of the IBC being invoked by operational creditors against the petitioner.
 
The Court held that the import of the decisions in K. Kishan  and Mobilox was that operational creditors ought not to be permitted to initiate CIRP in case there was a pre-existing dispute. In the present facts, the award existed 9 years prior to the initiation of the CIRP, and also was subject matter of challenge under Section 34 of the Act. In view of the law as aforesaid, the respondent award-holder could not have filed a claim before the NCLT/IRP since the Section 34 proceedings had not been decided in favour of the said respondent in 2017 and hence there was no final or adjudicated claim as on that date.
Further, once the stage under section 14 of the IBC, namely, moratorium with regard to continuation of pending proceedings against the Corporate Debtor has been declared to be over, no further embargo remains for continuing to hear suits and other proceedings to which the Corporate Debtor is a party. In any event, Section 14(a) contemplates suits or continuation of pending proceedings "against" the Corporate Debtor.
 
In this case, the petitioner being the Corporate Debtor/Award Debtor cannot be permitted to take shield under the provisions of the IBC for relegating the claim of the respondent award-holder to for an indefinite period of time on the ground of the respondent not having gone before the NCLT.
 
The application under Section 34 was therefore fixed for hearing.


 

Judgment delivered by the Punjab and Haryana High Court Rajender Sharma vs. Tanmay Developers Pvt. Ltd.

[CR-4079-2019 (O&M); MANU/PH/1975/2019]
 

The respondent filed its objections to the award by way of an application under Section 34 of the Act. The petitioner (claimant) filed their reply to the above application praying for dismissal of the said application. The respondent moved an application for granting permission to file rejoinder to the reply filed by the petitioner. The application for filing the rejoinder was allowed and the parties were directed to furnish proper affidavits in support of the pleadings.
 
Hence, the present revision was filed by the petitioner before the High Court for setting aside the order by which an application seeking permission to file rejoinder moved on behalf of the respondent was allowed as well as the order, directing the parties to furnish proper affidavit in support of the pleadings.
 
The Court placed reliance on the judgment of the Supreme Court in Emkay Global Financial Services Limited vs. Girdhar Sondhi [(2018) 9 SCC 49] wherein it was held that applications under Section 34 of the Act ought to be decided ordinarily on the basis of the record of the Arbitrator. In the event that there were matters which were relevant to the determination of an issue under Section 34(2)(a) which did not form part of the record, the same could be brought to the notice of the Court hearing the application under Section 34. Cross examination was ordinarily to be avoided, unless absolutely necessary.
 
Applying the above position of law, it was held that the direction in question, viz., to file their affidavit in support of the pleadings was absolutely not necessary as it was not the case of the respondent that they were praying for setting aside of the Award on the basis of material, which was not there in the record.
Further, it was observed that the filing of an affidavit along with pleading will apply to a suit and not to an application under Section 34 of the Act.
 
On the issue of the filing of the rejoinder, it was held that notwithstanding the absence of a requirement to do so, the filing of a reply to the Section 34 application was permitted by the Court below and therefore the filing of a rejoinder could not be objected to.


 

Judgment delivered by the Rajasthan High Court State of Rajasthan vs. M.M.C. Projects (India) Pvt. Ltd. and Anr.

[S.B. Civil Misc. Appeal No. 2229/2016; 2019 SCC OnLine Raj 4897]
 

The appeal before the High Court arose from an order passed by the District Judge, whereby, the application preferred by the appellant under Section 5 of the Limitation Act along with the application under Section 34 of the Act for setting aside the arbitral award was rejected, as being time barred.
 
The Court observed that Section 34(3) provided that an application for setting aside of the arbitral award may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under Section 33, from the date on which that request had been disposed of by the arbitral Tribunal. The proviso to Section34(3) of the Act empowers the Court if it is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months to further extend the period and filing of the application for setting aside of the arbitral award by 30 days but not thereafter.
 
By relying on the judgment of Simplex Infrastructure Limited vs. Union of India (2019) 2 SCC 455, it was held that Section 5 of the Limitation Act is not applicable to an application challenging an arbitration award under section34 of the Act and the present application, filed by the Appellant was beyond the mandatory limitation period provided under section34(3) of the Act and hence, the same could not have been entertained by taking recourse of the provisions of the Limitation Act.