PAYMENT OF WAGES DURING LOCKDOWN- LEGALITY OF THE MHA ORDERS UNDER THE DMA ACT, 2005
 
In Ficus Pax Pvt. Ltd. v. Union of India &Ors., the Supreme Court has been called upon to examine the legality of the Orders dated 20.3.2020 issued by the Ministry of Labour and Employment and 29.3.2020 issued by the Ministry of Home Affairs, Govt. of India whereby directions were issued to all States under Section 10(2)(l) of the Disaster Management Act,  2005 to ensure that all establishments to continue to pay wages during the period of the lockdown, irrespective of whether the employees attend work or not.
 
The orders are to be tested on the anvil of Articles 14 and 19(1)(g) of the Constitution of India, on the ground of being contrary to the principle of Equal Work Equal Pay and No Work No Pay. Among other grounds, the availability of Section 10(2)(l) to impose financial obligations on private employers has also been questioned. The constitutional validity of the said provision itself is also under challenge.
 
The said orders have since been withdrawn by the Central Government (w.e.f. 18.5.2020). The question that remains is the applicability and validity of the said orders during the period of their operation. The Supreme Court has called upon the Central Government to file its detailed response to the petitions, and in the meanwhile issued the following interim directions:
 
(i)                The interim direction prohibiting any coercive action for non compliance of the orders has been continued;
(ii)             Private establishments have been urged to enter into a negotiated settlement with their employees for payment of wages during the period of lockdown, and if such a settlement is arrived at, the same be given effect to notwithstanding the orders dated 20.3.2020 and 29.3.2020;
(iii)           The private establishments to permit the workers and employees to continue to work, without regard to their demand for payment during the period of lockdown.
 
The petitions have now been listed for hearing in the last week of July.
 
PERIOD OF LIMITATION UNDER ARTICLE 113 IS TO BE RECKONED FROM THE DATE OF ACCRUAL OF THE CAUSE OF ACTION, AND NOT THE DATE OF FIRST ACCRUAL OF CAUSE OF ACTION
 
Shakti Bhog Food Industries Ltd. v. The Central Bank of India &Anr. arose out of a suit initiated by the Appellant against the Respondent for rendition of accounts in relation to interest charged by the Respondent on the current account of the Appellant as also for recovery of the excess amount charged by the Respondent. The suit plaint came to be rejected under Order VII Rule 11 of the Civil Procedure Code, 1908 as being barred by limitation.
The Appellant’s reference to the date of rejection of its’ representation to the Respondent as the commencement of the period of limitation was rejected by the Courts below relying, inter alia on the decisions of the Supreme Court wherein it was held that the correspondence between parties could not be relied upon to extend the period of limitation.
 
The Supreme Court examined the plain meaning of Article 113 of the Schedule to the Limitation Act, 1963 wherein the expression used is ‘when the right to sue accrues’ and not ‘when the right to sue first accrues’. It was found that in the present facts, the rejection of the representation of the Appellant by the Respondent would be the date of accrual of cause of action for the purpose of Article 113 (being a firm denial by the Bank) since until then the Appellant had a sanguine hope of a favourable resolution. The decisions of the Court relied upon by the Respondent were distinguished since they did not deal with Article 58 of the Schedule.
 
The Court further held that the case was not one which was fit for rejection of plaint under Order VII Rule 11(d) of the CPC since the question of limitation is a mixed question of law and facts.
 
SCOPE OF THE ‘NATURAL JUSTICE’ GROUND UNDER SECTION 48(1)(b) OF THE ARBITRATION AND CONCILIATION ACT, 1996
 
In M/s Centrotrade Minerals and Metals Inc. v. Hindustan Copper Ltd., a Bench of three Hon’ble Judges of the Court heard and disposed off a reference arising from a difference of opinion of two Hon’ble Judges in the matter of enforcement of a foreign award. The arbitration clause between the parties provided for a two tier arbitration procedure, where the arbitration award of the Indian arbitral tribunal was to be tested by the ICC Arbitral Tribunal in London.
 
The difference of opinion between the two Hon’ble Judges on the question of validity of such an arbitration clause was answered by three Judges of the Court in 2017. The only question remaining for examination was whether the Respondent in the present case (the judgment debtor under the award) was granted sufficient opportunity of hearing in terms of Section 48(1)(b).
 
The Court examined a plethora of case law on the ‘inability of a party to present its case’ as a ground for resisting enforcement of the award, and relied upon and reiterated the ratio in Vijay Karia v. PrsymianCavi E Sistemi SRL that a good working test to determine whether a party has been unable to present his case is to see whether factors outside the party’s control have combined to deny the party a fair hearing. Applying the test to the facts of the case, it was found that matters could not be said to be outside the control of the Respondent so as for it to be able to claim ‘inability to present its case’.
 
The Court also held that the ‘remand’ of a proceedings under Section 48 to the arbitral tribunal to deliver a fresh award, as had been done by one of the two Hon’ble Judges, was beyond the powers of the Court under Section 48.
TAXABLE EVENT OF SALE IN A WORKS CONTRACT IS THE USE OF GOODS/MATERIALS IN THE EXECUTION OF THE CONTRACT
 
State of Orissa v. M/s B. Engineers & Builders Ltd. arose from a writ petition filed by the Respondent before the High Court, challenging certain circulars of the Appellant whereby the benefit of reimbursement of sales tax paid during the course of execution of the works contract by the Respondent, and granted under a clause of the General Conditions of Contract between the parties, was sought to be withdrawn by way of the said circulars.
 
The case of the Appellant was that since the relevant clause in the GCC provided for reimbursement of Central and State sales tax and other taxes on completed items of works as may be levied and paid by the employer on proof of payment and production of assessment certificate, and since the contract in question was a works contract wherein the ‘completed item of work’ was not assessable to sales tax, the same was not reimbursable to the Respondent.
 
The Court examined the Constitutional history of Article 366(29-A)(b) whereby the concept of a deemed sale was introduced in works contracts, thereby empowering the States to tax the sale of goods involved in the execution of a works contract. Thus, even in the case of the contract of the Respondent, the sales tax levied and paid by the Respondent was reimbursable. This is because sales tax was levied and paid on the goods involved in the execution of the works contract (as was also factually observed). For the purposes of sales tax in a works contract, the taxable event was the use of materials involved in the execution of the works contract.
 
DEDUCTION UNDER SECTION 80-O OF THE INCOME TAX ACT: LIBERAL CONSTRUCTION NOT MERITED UNLESS THE THRESHOLD REQUIREMENT FOR APPLICABILITY IS SATISFIED
 
In Ramnath & Co. v. The Commissioner of Income Tax, the Court was called upon to examine the claim by the Appellant for deduction, under Section 80-O of the Income Tax Act, 1961, of the income received by the Appellant in foreign exchange, for services provided by the Appellant to foreign enterprises. It was the case of the Revenue that the Appellant was merely an agent of the foreign company, and was thus not entitled to a deduction.
 
Among others, it was the argument of the Appellant that since the object of the said provision is to incentivise earnings in foreign exchange, the provision ought to be liberally construed. On facts, the Appellant relied on the terms of its agreement with the foreign enterprise to show that the agreement required provision of an ongoing service, and was not merely a contract whereby the Appellant was appointed as a procuring agent in India.
 
The first argument was rejected by the Court while relying on the Constitution Bench decision in Commissioner of Customs (Import), Mumbai v. Dilip Kumar & Co. and Ors., wherein it was held that exemption notifications are to be construed strictly. Holding that exemptions, deductions etc. all belonged to the species of incentive, the Court concluded that the ratio in Dilip Kumar was applicable. It was only once the eligibility of the assessee for the incentive was satisfied, that the provision could be construed liberally.
 
On facts, on a reading of the provisions of the agreement, the Court found that the appellant merely acted as agent of the foreign enterprise, and was thus not entitled to claim the deduction.
 
ELECTRICITY DUES, BEING STATUTORY DUES CANNOT BE WAIVED- AUCTION PURCHASER IN SARFAESI AUCTION HELD LIABLE TO CLEAR PREVIOUS DUES ON PROPERTY
 
In Telangana State Southern Power Distribution Company Ltd. &Anr. v. Srigdhaa Beverages the question was whether an auction purchaser who had purchased a unit of a debtor in an auction conducted under the Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (“SARFAESI”) could be saddled with the liability on account of electricity dues of the said debtor.
 
In the facts, the Court found that the auction notice itself provided for sale of the property on ‘as is where us whatever there is and without recourse basis’, and also specifically referred to electricity dues. In case of an auction notice as in the present case, it was incumbent upon the prospective bidder to make necessary enquiries to ascertain the exact status of the dues.
 
Additionally, the Court reiterated that electricity dues partake a statutory character and the licence or the agreement were merely for the purpose of bringing to the notice of the consumer the terms and conditions of supply. This being the case, they could not be held to be waived.