The question in this appeal was as to whether a writ petition under Article 226 of the Constitution of India could be entertained against an assessment order on the sole ground that the statutory remedy of appeal against the order stood barred by law.
 
An assessment order passed by the appellant against the respondent under the Andhra Pradesh Value Added Tax Act, 2005 was not challenged by the respondent within the stipulated time period under the applicable rules. The delay was sought to be explained by placing the blame on negligence of an employee of the respondent, against whom disciplinary proceedings had also been initiated. The appellate authority disbelieved the factual version set up by the respondent, and also rejected the appeal on the ground that the delay in the case was beyond its power of condonation under the statute. This order of the appellate authority was not challenged further. Instead, the original assessment order was challenged by way of a writ petition before the High Court, which writ petition of the respondent came to be allowed by the order under challenge before the Supreme Court.
 
The Supreme Court held:
 
(i)                 Although power under Article 226 is wide, it ought usually not to be exercised where alternative remedy is available to a party; the Court relied on Titaghur Paper Mills Co. Ltd. &Anr. v. State of Orissa &Ors. for the proposition that where a right or liability is created by statute which gives a special remedy in enforcing it, that statutory remedy must only be availed of;
(ii)               The power of the High Court under Article 226 cannot be exercised to issue a writ which would be inconsistent with the legislative mandate. The decisions of the Andhra High Court in Electronics Corporation of India Ltd. v. Union of India &Ors., of the Gujarat High Court in Panoli Intermediate (India) Pvt. Ltd. v. Union of India &Ors., and of the Karnataka High Court in Phoenix Plasts Company v. Commissioner of Central Excise (Appeal-I), Bangalore were held to proceed on a fallacious premise.
(iii)             Once the statute provides a remedy, and the statutory remedy of appeal has been allowed to become time barred, the question of violation of fundamental rights so as to entertain a writ petition could not arise.
 
The appeal was thus allowed.
 
South East Asia Marine Engineering and Constructions Ltd. (Seamec Ltd.) v. Oil India Limited
[Civil Appeal No. 673 of 2012 decided on 11.5.2020]
 
This case arose out of a challenge to a judgment of the Gauhati High Court whereby the High Court, in exercise of power under Section 37 of the Arbitration & Conciliation Act, 1996 (“Act”), set aside an arbitral award while holding that the interpretation of the contract by the arbitral tribunal was against the public policy of India. The award having been upheld under Section 34, the High Court opined that the award could be set aside under Section 37 as it had been passed overlooking the terms and conditions of the contract.
 
The bone of contention between the parties was the applicability of Clause 23 of the contract between the parties (for drilling of oil wells in Assam by the appellant for the respondent) which was the ‘Change in Law’ clause. During the subsistence of the contract, the Government by an executive order brought about an increase in the price of High Speed Diesel (HSD) which was one of the essential materials for carrying out drilling operations. The appellant claimed that this triggered Clause 23, and the respondent was liable to reimburse the increase to the appellant. The arbitral tribunal accepted the claim of the appellant while holding that the executive action though not strictly ‘law’ within the meaning of Clause 23, did have the force of law. This view was reversed by the High Court while holding that Clause 23 of the contract was akin to a force majeure clause relatable to Section 56 of the Contract Act, 1872.
 
The Supreme Court held:
 
(i)                 Clause 23 of the contract was found to be one which envisaged and dealt with the harsh consequences of a possibility of frustration of the contract, and provided for measures for mitigation of the same;
(ii)               It was found that Clause 23 did not support as wide an interpretation as canvassed by the appellant, and sustained by the arbitral tribunal; It was observed that the thumb rule of interpretation of a written contract was to read it as a whole and so far as possible, mutually explanatory;
(iii)             It was found that the contract was one for a fixed price, and the risk of price fluctuation was limited by the terms of the contract, and can also have been assumed to have been taken into account by the bidder while bidding for the tender;
(iv)             The wide interpretation of Clause 23 to include price variation in HSD was also not supported by the other terms of the contract. The Court also noticed that fuel was to be provided by the contractor at his expense. This was found to be another indicator of the fact that the view of the arbitral tribunal was not a possible interpretation of the terms of the contract.
 
The impugned order was sustained and the appeal was dismissed based on the above conclusions.
Patel Engineering Ltd. v. North Eastern Electric Power Corporation Ltd. (NEEPCO)
[S.L.P (C) 3584-85/2020 and connected matters decided on 22.5.2020]
 
The SLPs before the Supreme Court were filed against a set of impugned orders dated 10.10.2019 of the High Court of Meghalaya at Shillong whereby the High Court refused to entertain review petitions filed by the petitioner in respect of a judgment and order dated 26.2.2019. The review petitions were dismissed on the ground of delay as well as the finding that no ground for review was made out.
 
The orders dated 26.2.2019 had been passed by the High Court to allow the appeals under Section 37 of the Arbitration & Conciliation Act, 1996 (“Act”) filed by the respondent against the order of the Additional Deputy Commissioner (Judicial) who had rejected the respondent’s application under Section 34 challenging the arbitral awards passed in favour of the appellant. The arbitral awards had thus been set aside by the High Court.
 
The aforesaid orders dated 26.2.2019 were challenged by the appellant before the Supreme Court, and the special leave petitions came to be dismissed by a non-speaking order on 19.7.2019. No leave to file review before the High Court was sought at the stage of dismissal of the SLPs on 19.7.2019.
 
Nevertheless, review petitions came to be preferred by the appellant before the High Court on the ground that while passing the Orders dated 26.2.2019 the High Court had committed an error apparent on the face of the record in failing to consider the amendments made to the Act by the Amendment Act of 2015. The said review petitions were dismissed vide the Orders dated 10.10.2019, subject matter of the present challenge.
 
The Supreme Court referred to and relied upon its decision in Bussa Overseas and Properties Private Limited and Another v. Union of India and Another to hold that the present SLPs were not maintainable against the Orders whereby applications for review had been rejected, especially also since the appellants had not sought liberty to approach the High Court for review at the stage of dismissal of the first round of SLPs.
 
On the merits of the challenge, the Supreme Court held that the High Court had correctly applied the law in Associate Builders v. Delhi Development Authority (which was followed inSsyangyong Engineering and Construction Company Limited v. National Highways Authority of India) to hold that a domestic award could be set aside on the ground of patent illegality or if the view of the arbitrator was found to be perverse. The mere reference to judgments which preceded the Amendment Act of 2015 could not lead to the conclusion that the High Court had applied the principles of law incorrectly.
 
The impugned orders were upheld and the appeals were dismissed.